Contracting client
Aurora New Energy Technology Company
Taking over the team
Hengtong installation team
Project leader
Gao Min
Contract amount
¥980,000
Start date
2026-04-02
Planned completion
2026-06-30
Project address
Ningbo Yinzhou District Smart Industrial Park
Current progress
45%
Project Milestones
- Site surveyComplete 2026-04-02
- Quote confirmationComplete 2026-04-19
- Entering the market to explainComplete 2026-05-07
- 4Main constructionPlan 2026-05-25
- 5Completion acceptancePlan 2026-06-12
- 6Settlement and invoicingPlan 2026-06-30
Construction schedule
Weekly view · Progress filling
Task
3/30
4/6
4/13
4/20
4/27
5/4
5/11
5/18
5/25
6/1
6/8
6/15
6/22
6/29
Site survey
100%
Quote confirmation
100%
Entering the market to explain
100%
Main construction
45%
Completion acceptance
Project news
NoteRecorded a grounding issue in the distribution box for remediation
2026-06-03 10:05 · Gao Min