Contracting client
Ruikang Pharmaceutical Co., Ltd.
Taking over the team
Golden Dome Decoration Team
Project leader
Zhou Lei
Contract amount
¥1,740,000
Start date
2026-02-18
Planned completion
2026-06-15
Project address
Suzhou Industrial Park Biomedical Industrial Park C3
Current progress
88%
Project Milestones
- Site surveyComplete 2026-02-18
- Quote confirmationComplete 2026-03-13
- Entering the market to explainComplete 2026-04-05
- Main constructionComplete 2026-04-29
- 5Completion acceptancePlan 2026-05-22
- 6Settlement and invoicingPlan 2026-06-15
Construction schedule
Weekly view · Progress filling
Task
2/15
2/16
2/23
3/2
3/9
3/16
3/23
3/30
4/6
4/13
4/20
4/27
5/4
5/11
5/18
5/25
6/1
6/8
6/15
Site survey
100%
Quote confirmation
100%
Entering the market to explain
100%
Main construction
100%
Completion acceptance
88%
Project news
MilestoneCleanliness test passed; preparing for final acceptance
2026-06-02 15:00 · Zhou LeiPhotoUploaded 5 acceptance photos of the ceiling supply-air outlets
2026-05-28 13:20 · Golden Dome Decoration Team